Education

Little Ilford School

Little Ilford School

Scope of Works

Lift & Locate were allocated to the Little Ilford project to provide their full turnkey package. A logistics survery was carried out at tender stage to ensure the viability of the project.

The Challenge

The building is on a steel gantry, above a car park, and has a curved design with two traditional staircases each end. Setting out of the building was key to ensure we adhered to their tolerances and ensured a smooth install.

We recently completed one of our largest education projects, Little Ilford Secondary School in Newham, London.

We installed this large new three-storey multi-functional teaching block with classrooms and corridors, an activity studio and ancillary staff rooms.

  • Comprehensive logistics survey completed prior to clients tender submission Transport
    managed by Lift & Locate from factory to site
  • Install sequence completed to maximise efficiency
  • Lift plan and RAMS completed
  • Crane organised and managed on site for installation
  • Install on site for 56 modules
  • Following our logistics survey, parking suspensions and road closures arranged to ensure
    modules could get to site
  • Full fit out internally and externally

Lift and Locate were able to meet the challenges safely and efficiently from the outset. The team tackled this project head on and the 2 week install ran smoothly.

Ryan Geldard, Director

Related Projects

Education

Temporary School, Newcastle Upon Tyne

Located on a tight site in a residential area in Newcastle Upon Tyne, Lift & Locate installed a 52 module temporary school following the discovery of Reinforced Autoclaved Aerated Concrete (RAAC) in their ceiling panels.

Education

Temporary School, Newcastle Upon Tyne