What an incredible end to 2023…1 Charter Street, Canary Wharf. Our proudest achievement to date!
For the last 12 months we have been installing an 18 storey modular hotel in Canary Wharf. The project bought many challenges for us as a business, but we could not be more proud of what the team have accomplished.
- Transport managed by Lift & Locate
- 340 modules transported between factory, storage site and Canary Wharf
- Effective sequencing to ensure ‘just in time’ arrival to site holding yard
- Storage Yard sourced and managed throughout
- Crane on storage site organised and managed
- Install on site for 340 modules (18 storeys)
- Lifting equipment sourced and supplied by Lift & Locate
A huge thank you to our partners Modular Movements Ltd, MGA CRANE HIRE LIMITED and to all of the Canary Wharf Group team, we couldn’t have done it without you all!